Introduction
This essay addresses the legal and contractual issues faced by Commercial Re-developments Ltd concerning the defective construction works carried out by JW Civils Ltd in the development of an events building. The focus is on the liability of JW Civils Ltd for losses incurred due to defective external walls and foundations, as outlined in the provided scenario under the law of England and Wales. As a student of Quantity Surveying, this analysis will consider contractual obligations, relevant legal principles, and limitation periods that impact the potential claims. The essay will first explore the contractual framework and duty of care, followed by specific analysis of liability for the external walls and foundations, including associated damages. Finally, it will conclude with a summary of key arguments and implications for Commercial Re-developments Ltd in pursuing remedies.
Contractual Framework and Duty of Care
In construction projects, contractual agreements often define the responsibilities and liabilities of parties involved. The scenario indicates that JW Civils Ltd was awarded the package for the design and construction of foundations and external walls, with an explicit obligation to use reasonable skill and care in their design and execution. This aligns with common provisions in construction contracts, such as those under the JCT (Joint Contracts Tribunal) framework, which typically impose a standard of reasonable skill and care on contractors and subcontractors for design elements they undertake (Lupton, 2019).
Additionally, under the law of England and Wales, there exists a general duty of care in tort, established in cases such as Donoghue v Stevenson [1932] AC 562, which may apply where contractual remedies are insufficient. However, tortious liability in construction is often limited by the principle of economic loss, as clarified in Murphy v Brentwood District Council [1991] 1 AC 398, where the courts have been reluctant to impose liability for pure economic loss unless a special relationship or assumption of responsibility exists (Peel and Goudkamp, 2020). For Commercial Re-developments Ltd, the primary avenue for redress will likely be contractual, focusing on breaches by JW Civils Ltd, though tortious claims might be considered as a secondary option.
Liability for Defectively Constructed External Walls
The defective construction of the external walls, which became evident thirty months after completion, resulted in a seven-month closure of the events building for repairs. Under a typical construction contract, defects arising from poor workmanship or failure to adhere to design specifications constitute a breach of contract. Given that JW Civils Ltd was responsible for both design and construction, their obligation to exercise reasonable skill and care is central to assessing liability.
Importantly, the timing of the defect’s discovery raises questions about limitation periods under the Limitation Act 1980. For contract claims, the standard limitation period is six years from the date of breach, which, in construction, is generally taken as the date of practical completion (Section 5, Limitation Act 1980). Assuming practical completion occurred at or around project completion, a claim for the external wall defects may fall outside this period if initiated more than six years after completion. However, if a longer limitation period of twelve years applies (e.g., if the contract was executed as a deed under Section 8 of the Limitation Act 1980), a claim might still be actionable. Commercial Re-developments Ltd must confirm the nature of the contract to ascertain the applicable period.
Moreover, losses incurred due to closure and repairs—likely including direct costs of remediation and consequential losses such as loss of revenue—could be recoverable if proven to stem from JW Civils Ltd’s breach. Quantity surveyors often play a role in quantifying such losses, ensuring that claims are supported by detailed cost breakdowns and evidence of impact (Cartlidge, 2017). Therefore, while liability for the external walls seems plausible, the enforceability of a claim hinges on the limitation period and the availability of robust financial evidence.
Liability for Defectively Constructed Foundations
The defective construction of the foundations, which caused structural movement and subsequent cracks evident seven years after completion, presents a more complex issue. The cracks led to a suspended ceiling collapse eighteen months later, damaging fit-out works and necessitating further closure of the events space. A structural engineer’s report attributes this to negligence in foundation construction, strengthening the case for JW Civils Ltd’s liability.
From a contractual perspective, the failure to construct foundations with reasonable skill and care constitutes a clear breach. However, the extended timeframe before the defect became apparent—seven years—poses significant challenges due to limitation periods. As with the external walls, a six-year limitation period for standard contracts would likely bar a claim unless the contract was executed as a deed, allowing for a twelve-year period. Furthermore, under Section 14A of the Limitation Act 1980, an alternative three-year period may apply for negligence claims in tort, starting from the date when the claimant had knowledge of the damage. Given that Commercial Re-developments Ltd discovered the cracks seven years post-completion, this provision might offer a limited window for a tortious claim, though pure economic loss limitations in tort (as per Murphy v Brentwood) could constrain recovery (Peel and Goudkamp, 2020).
The collapse of the suspended ceiling and resultant damage to fit-out works (furniture, audio-visual, and ICT equipment) represent consequential losses. In contract law, losses that are reasonably foreseeable at the time of contract formation can be claimed, as established in Hadley v Baxendale (1854) 9 Ex 341. Damage to fit-out works and closure costs could arguably fall within this scope, provided causation is clearly linked to the defective foundations. Quantity surveyors would again be instrumental in assessing and documenting these losses to support a claim (Cartlidge, 2017). However, the long delay in discovering the defect and the potential expiration of limitation periods remain significant hurdles.
Broader Implications and Challenges
Several broader issues must be considered by Commercial Re-developments Ltd. First, the insolvency of Events Space Builders Ltd, the main contractor, six months after completion complicates the chain of responsibility. Typically, the main contractor bears primary responsibility for subcontractors’ work, but insolvency may prevent recovery from them, forcing direct claims against JW Civils Ltd. Second, the decision to opt for JW Civils Ltd due to social value outcomes, despite an alternative recommendation, does not absolve JW Civils Ltd of liability but may raise questions about due diligence in contractor selection.
Additionally, latent defects—those not immediately apparent—often fall under specific contractual provisions or statutory protections, such as the Defective Premises Act 1972. Under Section 1 of this Act, a duty is imposed on those involved in construction to ensure work is done properly, with a six-year limitation period from completion. However, this applies primarily to dwellings, and its applicability to a commercial events space is uncertain without further legal clarification (Murdoch and Hughes, 2008). Therefore, reliance on contractual remedies appears more viable, subject to limitation constraints.
Conclusion
In advising Commercial Re-developments Ltd, it is evident that JW Civils Ltd bears potential liability for both the defectively constructed external walls and foundations, based on their contractual obligation to exercise reasonable skill and care. For the external walls, defects identified thirty months post-completion may still be actionable if the contract allows for a twelve-year limitation period or if alternative legal provisions apply. For the foundations, the delayed discovery of defects seven years after completion poses greater challenges, though tortious claims under extended limitation rules might offer a narrow window for remedy. Consequential losses, including closure costs and damages from the ceiling collapse, could be recoverable if causation and foreseeability are established. However, limitation periods and the insolvency of Events Space Builders Ltd present significant obstacles. Commercial Re-developments Ltd must urgently review contractual documentation and seek legal counsel to confirm applicable limitation periods and quantify losses, ideally with input from quantity surveyors to ensure claims are robust and evidenced. The broader implication is the critical need for thorough contractor vetting and clear contractual terms to mitigate risks in future developments.
References
- Cartlidge, D. (2017) Quantity Surveyor’s Pocket Book. 3rd ed. Routledge.
- Lupton, S. (2019) Guide to JCT Standard Forms of Building Contract. RIBA Publishing.
- Murdoch, J. and Hughes, W. (2008) Construction Contracts: Law and Management. 4th ed. Taylor & Francis.
- Peel, E. and Goudkamp, J. (2020) Winfield & Jolowicz on Tort. 20th ed. Sweet & Maxwell.

